July 29, 2026|Client Alerts
FERC Issues Show-Cause Orders: Impacts on California
By Gwenneth O’Hara, Antonio Carrejo
Insights
July 29, 2026|Client Alerts
By Gwenneth O’Hara, Antonio Carrejo
Background
On June 18, 2026, the Federal Energy Regulatory Commission (FERC) issued six show cause orders individually directed at the each of the regional grid operators under its purview. The orders are the result of the Secretary’s October 2025 advance notice of proposed rulemaking directing FERC to consider taking additional actions to address the addition of large and co-located loads to the transmission system.
Rather than issuing a broad final rule, FERC took a region-by-region approach, recognizing differences in market structure, stakeholder landscape, geography, and progress in addressing large-load integration. FERC states that the orders are intended to address rapidly growing demand from data centers.
FERC directed the RTOs and ISOs to address five key issues:
Applicability to California
The California Independent System Operator (CAISO) is one of the entities covered by FERC’s show cause orders. Therefore, California data center developers may see changes to transmission service rules, interconnection procedures, study requirements, and large-load tariff structures.
Compared to the other regions served by RTOs/ISOs, California faces distinct challenges due to rapidly growing electricity demand from data centers, electric vehicle charging, and broader electrification trends. The California Energy Commission projects that data center demand alone could increase by 1.8 GW by 2030 and 4.9 GW by 2040.
Unlike other RTOs/ISOs, CAISO does not provide traditional network integration or point-to-point transmission service, long-term firm transmission reservations, or a formal transmission-service application process. Instead, transmission access is generally provided through CAISO’s market framework, while transmission owners (TOs) take the lead on physical load interconnection. As a result, FERC’s concerns extend to both CAISO and its transmission-owning members. FERC’s show-cause order identifies several areas where CAISO’s current framework may be insufficient to support the growing number of large-load customers, particularly data centers. The Order finds that CAISO’s existing Open Access Transmission
Tariff and/or the Transmission Owner Tariffs of the Participating Transmission Owners appear to be unjust, unreasonable, or unduly discriminatory or preferential. CAISO has 60 days to demonstrate why its existing tariff provisions are just and reasonable. FERC also directed CAISO to submit an informational report on how CAISO intends to ensure that adequate generation will be available to serve existing and new large loads.
Key FERC Concerns in the CAISO Show Cause Order
Large-Load Study Process:
FERC is concerned that CAISO lacks a clear and coordinated framework for evaluating large-load interconnection and transmission needs. The division of responsibilities between CAISO and transmission owners could lead to delays, duplicative requests, inefficient upgrades, and uncertainty over accountability.
Cost Shifting and Cost Transparency:
FERC questioned whether CAISO has adequate safeguards to prevent transmission costs associated with large loads from being shifted to existing customers. The agency also cited a lack of transparency regarding which transmission costs are driven by large-load development.
Co-location and Behind-the-meter generation:
FERC believes CAISO’s tariff may not provide sufficient guidance for co-located facilities and behind-the-meter generation serving large loads. Key concerns include transmission service requirements, ancillary service obligations, grid withdrawals, and avoiding cost shifting.
Flexible Transmission Service:
FERC noted that CAISO currently provides limited transmission-service options for large loads that can operate flexibly or intermittently. The agency asked CAISO to justify why additional flexible service products, such as non-firm or contract-demand services, are unnecessary.
Electrically Proximate Generation and Load:
FERC expressed concern that CAISO lacks tailored procedures for situations where generation resources are located close enough to large loads that they effectively function as a single electrical arrangement. Existing study processes may not fully account for these configurations.
Alternative Transmission Technologies:
FERC also expects CAISO to consider whether its planning and study processes should evaluate grid-enhancing technologies—such as dynamic line ratings, advanced conductors, and power-flow controls—before relying on traditional transmission upgrades.
Next Steps
This communication is not intended to create or constitute, nor does it create or constitute, an attorney-client or any other legal relationship. No statement in this communication constitutes legal advice nor should any communication herein be construed, relied upon, or interpreted as legal advice. This communication is for general information purposes only regarding recent legal developments of interest, and is not a substitute for legal counsel on any subject matter. No reader should act or refrain from acting on the basis of any information included herein without seeking appropriate legal advice on the particular facts and circumstances affecting that reader. For more information, visit www.buchalter.com.